About the Project
Pittsburgh Regional Transit (PRT) is progressing towards 90% design for the redevelopment of the Carnegie Station complex. The existing park and ride, operator relief facility, and station are located on PRT-owned property in Carnegie Borough, Allegheny County, PA, at the terminus of the West Busway.
Today, the complex contains approximately 200 surface lot parking spaces for riders, a 24’x8’ station shelter for boarding, one (1) single-occupancy operator restroom facility, and a layover area for five (5) 40’-buses.
This redevelopment initiative focuses on modernizing the bus station area to significantly improve daily operations and the overall transit experience. The project aims to increase layover capabilities and upgrade operator amenities, enhance safe and accessible boarding for paratransit services, and revitalize the station area to create a modern, efficient hub forthe region.
Main features of this project include:
- Expansion of the boarding platform to accommodate loading of two (2) articulated buses
- New modern shelter canopy spanning the full platform for covered loading
- Passenger drop-off and pick-up area close to the boarding area
- Dedicated space for paratransit vehicle parking
- A new, larger, relief facility for Operators
- Space for overhead charging equipment to power multiple electric buses
- Increasing bus layover capacity
- Surface lot repaving
- Bike parking
- New sidewalks
- Updated wayfinding signage
Additional work to enhance the ADA access to Mansfield Boulevard will be considered pending the outcome and timeline of the railroad being converted to rails to trails. Information on that endeavor can be found on the Borough’s website: https://carnegieborough.com/trail/support.html
Update
September 2026
Progressing towards 90% design, stay tuned for public meeting schedule announcement
Project Location
The map shows the location of Carnegie Station and park and ride at the southern end of PRT's West Busway where West Main Street intersects with Mansfield Boulevard in Carnegie Borough.
The redesign of Carnegie Station complex has gone through a few iterations over the years, but the intent of the project has remained the same: enhance public, customer, and operator experience.
The last major project update was shared with the community in November 2023. At that time, the proposed plans included a 5-story bus garage designed to accommodate pre-pandemic ridership levels.
While ridership continues to increase, recent trends show that passenger growth is stabilizing at a pace that no longer requires a facility of that scale. As a result, we have adjusted our plans to optimize the project while continuing to meet the region's current and future public transit needs.
All other core project features remain unchanged, including a separate passenger drop-off area with dedicated space for paratransit vans, larger and upgraded facilities for transit operators, and designated areas to evaluate potential future transit-oriented development (TOD).
PRT is engaging with the following partners during design:
- Carnegie Borough
- PennDOT
- Allegheny County Rails-to-Trails
- Genessee and Wyoming Railroad
Anticipated Construction Value: $15M
More information to be provided as design progresses
For detour and delay information: https://www.rideprt.org/Detours/
Timeline
-
Timeline item 1 - complete
Planning
2020 - 2022
-
Timeline item 2 - active
Design
October 2022 - Anticipated Summer 2027
-
Timeline item 3 - incomplete
Notice to Proceed Issued
-
Timeline item 4 - incomplete
Construction
-
Timeline item 5 - incomplete
Substantially Completion
Of Construction Activities
Past Public Meeting Recordings
Document Library
Current Design
Documents currently being developed
Past Public Meeting Presentations
-
Public Meeting Presentation - Summer 2020PDF (10.35 MB) -
Public Meeting Presentation - Fall 2020PDF (9.47 MB)
Archived Documents
Documents developed as previous concepts for the project